Development of Dawei SEZ - Overview

The development of Dawei SEZ will be done in Phases. Given its very ambitious scale, developing the full Dawei SEZ Project will take many years. To start the development of Dawei SEZ Project, and create jobs from day 1, the development of Dawei SEZ is done in phases. The various industries will be developed in phases, in line with the phased development of key infrastructures.

PictureTypeInitial Phase (2015-2020)Full Phase (after 2020)
SizeUp to 27 km2196.5 km2
Focus industriesLight and medium manufacturing, labour-intensive in natureHeavy manufacturing, scale and infrastructure-dependent in nature
Supporting infrastructureSet-up and development of infrastructureAddition, upgrade and enlargement of infrastructure
DeveloperTo be done by Consortium of Thai companies led by Italian-Thai Development PLCAllocation of individual projects to be determined by the Myanmar government